From version 3.3, Train Director allows scenario creators to specify both the behavior
and the appearance of individual signals.
The introduction of this functionality allows the display of the aspects of the signals
for distant signals, distant and protection signals, for signals specifying
a reduction in speed based on the selected itinerary and so on.
Moreover, it is now possible to display the signal aspects used by different
railroad administrations.
All of this is implemented by using text files that are independent from the
scenario. These files describe the icons to use, the behavior of the train when
approaching the signal, and how to decide the aspect of the signal based on
line conditions.
These text files are called "Train Director Scripts", or simply ".tds files".
A .tds file can be associated to one or more signals. The association
is specified through the "Signal Properties" dialog.

This is an example of a .tds file:
# One light signal (red,yellow,green)
Aspect: red
IconE: rE.xpm
IconW: rW.xpm
IconS: rS.xpm
IconN: rN.xpm
Action: stop
Aspect: yellow
IconE: yE.xpm
Action: proceed
Aspect: green
IconE: gE.xpm
Action: proceed
OnInit:
.aspect = red
end
OnCleared:
if .aspect = red
if next.aspect = red
.aspect =
yellow
else
.aspect =
green
end
end
end
OnUpdate:
if .aspect = red
return
end
if next.aspect = red
.aspect = yellow
else
.aspect = green
end
end
Let's describe each section of the file:
Comments
The first row of the file is a comment, and shows the type of the signal:
# One light signal (red,yellow,green)
All characters from the # included to the end of the row will be ignored by the program.
Comments are completely optional, so you don't have to use them. However
their presence is a big help to other authors who want to better understand
the logic of the file and to which signal to apply it to.
Aspects
The next section describes the various aspects that the signal can show:
Aspect: red
IconE: rE.xpm
IconW: rW.xpm
IconS: rS.xpm
IconN: rN.xpm
Action: stop
Aspect: yellow
IconE: yE.xpm
Action: proceed
Aspect: green
IconE: gE.xpm
Action: proceed
The name of the aspect is indicated by the "Aspect:" rows.
In this case we have 3 aspects: "red", "yellow", and "green".
For each aspect, it's necessary to specify the icon to display when the signal
is in the corresponding state "for each of the 4 directions",
east, west, north, south.
If the scenario does not use signals directed to north or south, the corresponding
directions can be omitted.
In this page's examples we'll only use the east direction,
assuming that the author will have to specify the other directions as well.
It is also possible to specify more than one icon per each direction. The various
icons will be displayed in sequence, going back to the first icon after the last
one has been displayed. This feature allows to "animate" the signal,
for example to show flashing signals.
In addition to the icon file, every aspect has associated an action, specified in the "Action:" rows.
This action will be executed when a train is traveling in the track section preceding the signal.
The possible actions are:
- "stop": the signal cannot be crossed. The train will stop
before the signal.
- "proceed": the signal can be crossed without specific
restrictions. The train will proceed beyond the signal.
- "speedLimit X": the signal can be crossed at
speed X (replace X with a number). The train will start to decelerate
before reaching the signal; that means that the signal behaves like
a speed limit associated to the track element linked to the signal.
- "none": the signal is ignored by trains; clicks
on the signal's icon will also be ignored. The signal is fully controlled
by the program. Distant signals use this action, since their aspect depends
solely on the condition of the track section after them.
With these simple instructions it's possible to create a number of cases,
so that one can describe the most common combinations.
The following sections tell to the program when to change the aspect
of the signal.
Events and Conditions
Obviously, a signal must change its aspect when certain conditions
on the layout occur. These conditions can be generated both by the player
and by trains movement.
Let's consider for each condition which actions can be applied.
OnInit : when the scenario is loaded
The actions associated with "OnInit:" are executed
when the scenario is opened the first time. Typically the associated action
is the definition of the initial aspect of the signal (usually red).
OnInit:
.aspect = red
end
Let's examine in greater detail the syntax to use in this section of the .tds file.
The section starts with the event that we are describing, that is "OnInit:".
After the name of the event, we specify a sequence of actions in the form of expressions.
In this case, ".aspect = red" means "change the signal aspect
according to the instructions in the "Aspect: red" section.".
Assigning a name to the aspect tells Train Director to change
the icon and the action associated with that signal, using the information specified
in the corresponding "Aspect:" section.
The use of the "dot" in ".aspect", indicates that we
are referring to the signal associated with this .tds file. We'll see later
how is possible to refer to other signals.
The section is always terminated by a row with the word "end".
OnCleared : the user clears the signal
When the user clicks on the signal's icon, if the following track section
is clear Train Director will examine the instructions associated to
the "OnCleared:" event to decide how to change
the signal's aspect. In this case, the actions to carry out are more complex:
OnCleared:
if .aspect = red
if next.aspect = red
.aspect =
yellow
else
.aspect =
green
end
end
end
As you can see, it's possible to query if certain conditions are valid by using the
"if" word. In the first row we are checking whether the current aspect
of the signal is red ("if .aspect = red"). If it isn't, the program
ignores all actions included between the "if" row and the corresponding
"end".
If instead the condition is true, the program continues with the execution
of the next row. In this example, we check what is the aspect of the next signal
after the current one ("if next.aspect = xxxx").
As you can see, the use if the word "next" before the word ".aspect"
tells Train Director to "look ahead" in the track section protected by
the signal. It is also possible to look ahead 2 or 3 track sections, by simply concatenating
multiple "next" words, as in "next.next.aspect".
Therefore, if the next signal is red ("if next.aspect = red"),
then the current signal should display a get ready to stop aspect; to do this,
we change its aspect to yellow (".aspect = yellow").
If instead the next signal is not red, Train Director will examine the actions
associated to the "else" word, in this case by changing the aspect
of the signal to green (".aspect = green").
Note how to each "if" always corresponds an "end" (2 ifs,
2 ends plus the end-of-section "end"). The convention to shift
to the right the instruction related to each "if" helps in
understanding which condition controls the execution of those instructions.
OnUpdate : another signal has changed aspect
When another signal on the layout has changed aspect, Train Director will execute
the instructions associated with the "OnUpdate:" section.
This allows changing the aspect of a signal when the signal in the controlled
track section changes aspect.
In our example:
OnUpdate:
if .aspect = red
return
end
if next.aspect = red
.aspect = yellow
else
.aspect = green
end
end
The logic is as follows: if the current signal is red, no action is performed;
the row with the "return" word tells Train Director to ignore
all the following instructions for this signal.
If the current signal is not red, then we need to look at the next signal
to verify its aspect ("if next.aspect = xxxx").
If the next signal has become red, then we need to change the aspect
of the current signal to yellow (".aspect = yellow").
If the next signal is not red, then we need to change the aspect
of the current signal to green (".aspect = green").
By specifying the signal's behavior in the way just described allows the representation
of many combinations specified in the "Regolamento Segnali"
of Trenitalia, and hopefully of other international railroad administrations.